Factory acceptance testing in China: how to approve made-to-order equipment before final payment
When equipment is manufactured or configured for a specific order, a standard visual check before shipment may not be enough. The buyer needs evidence that the finished system matches the agreed configuration, performs the required functions and can move to packing without unresolved critical issues. This is the purpose of a factory acceptance test, or FAT, at the supplier’s site. A useful FAT is not simply a demonstration that “the machine works.” It is a structured check against agreed acceptance criteria before final payment and shipment from China.
How FAT differs from a pre-order demonstration
A pre-order demonstration helps a buyer decide whether the general model, concept or operating principle is suitable. The supplier may show a standard sample, an available configuration or a similar system.
FAT takes place at a different stage. The order has already been placed, and the subject of the check is the actual equipment or system prepared for the buyer. The inspection therefore needs to cover not only general performance, but also the agreed configuration, settings, documentation and acceptance criteria.
A pre-order test answers: “Should we buy this type of solution?” FAT answers a different question: “Can we accept and pay for what has been built for our order?”
Agree the protocol before the order is ready
A weak FAT starts with the idea that everyone will decide what to test once the inspector arrives. In that situation, the supplier prepares a convenient demonstration, the inspector records observations, and the parties may later disagree about what counts as an acceptable result.
The working protocol should be agreed before production is complete. It should define:
- the exact identity of the unit and the agreed configuration; - the functions and operating modes to be demonstrated; - starting conditions and required connections; - the test sequence and expected result at each stage; - permitted deviations and clear fail conditions; - retest rules after correction; - the photos, video, readings and documents required in the report; - the decision supported by the result: accept, accept with conditions, rework or repeat FAT.
If a criterion cannot be observed or measured at the supplier’s site, this should be stated in advance. An inspection should not create the impression that something was confirmed when it was not actually tested.
Confirm site readiness before the visit
Even a good protocol will fail if the site is not ready. Before the inspector travels, the supplier should confirm in writing that the equipment is fully assembled, the correct configuration is available, and the necessary power, connections, consumables, tools and staff will be ready.
The inspector should also receive the latest specification, agreed changes and accessory list in advance. If these documents appear only during the visit, valuable time will be spent deciding which version of the order is final.
The duration of the full operating cycle also matters. Some functions take only a few minutes to demonstrate; others require more time or a specific sequence. A realistic plan includes setup, restart, result recording, possible retests and time for the supplier to address findings.
What happens during FAT
The first step is equipment identification. The inspector records markings, principal assemblies and available identifying data so the report clearly shows which unit completed the test.
The agreed configuration is then checked: components, accessories, interfaces, documentation and other items included in the order. The equipment is subsequently operated according to the approved scenario.
The record should cover more than the final result. Useful evidence includes the starting conditions, sequence of actions, actual system behaviour, messages and indications, operator involvement, stops, restarts and any deviations. Photos and video should be linked to specific protocol points, not presented as a general tour of the site.
If the supplier demonstrates a function differently from the approved method, that does not automatically mean failure. However, the change should be recorded, the reason explained and its effect on the reliability of the result stated clearly.
How to handle findings
Not every finding requires the order to be stopped. Every finding does, however, need a clear status and next action.
A practical report can separate results into four groups:
1. Passed — the criterion was met and evidence is attached. 2. Passed with a finding — the function was confirmed, but an agreed correction or document is still required. 3. Failed — the result did not meet the criterion; rework and retesting are required. 4. Not tested — the required conditions, access, time or equipment were not available.
“Generally working” is too vague for a commercial decision. The report should show which points are closed, which remain open, who is responsible for correction and what must be confirmed before payment or shipment.
After rework, it may not be necessary to repeat the entire FAT if the change affected only one area. The retest scope should still be agreed. In some cases, checking the corrected point is enough; in others, the change may affect connected functions and require part of the scenario to be repeated.
Connecting FAT to final payment
FAT is most useful when its role is written into the order terms in advance. The buyer and supplier should share the same understanding of which result allows the final payment stage to proceed and which findings require correction first.
This does not mean the inspector makes the financial decision for the buyer. The inspector collects evidence and compares it with the protocol. The buyer retains the payment decision and considers the report together with the contract and commercial terms.
FAT should also be kept separate from packing control. After a successful test, the equipment may be partly disassembled, completed with accessories or prepared for transport. If shipment contents, protection, markings and packing condition are important, they should be checked as a final block or during a separate visit.
What FAT does not prove
FAT records performance at the supplier’s site within the agreed protocol. It does not replace mandatory certification, laboratory testing, destination-market compliance review, installation or commissioning at the buyer’s site.
It also does not prove long-term reliability unless a separate endurance test is included. A short operating run is not the same as performance over the product’s service life. These limitations should be visible in the report so the result is not interpreted more broadly than the work actually completed.
What the buyer receives
A strong FAT result is not simply a folder of videos. It is a structured decision package containing:
- identification of the tested equipment; - the agreed protocol and actual test conditions; - a result for each acceptance criterion; - photos and video linked to inspection points; - deviations and test limitations; - correction and retest status; - a clear conclusion: accept, accept with conditions, rework or retest.
Majestic helps buyers prepare a FAT programme, coordinate it with the supplier, conduct the on-site check in China and present the result so the buyer can see verified facts and open points before final payment.
Summary
If equipment is being manufactured or configured for your order, send us the specification, agreed configuration and intended operating scenario. We will propose a realistic acceptance plan and explain which points can be verified at the supplier’s site and which require a separate procedure.
Need a check for your task?
Send the product, supplier and deadline. We will suggest the right verification plan.
Get a quote →